Annex: B
PHASE COMPLETION DATES (PCD)
|
Phase |
No. of Days |
Starting Date |
Completion Date |
|
I |
20 |
Sept. 25 |
Oct. 14 |
|
II |
35 |
Oct. 15 |
Nov. 17 |
|
III |
45 |
Nov. 18 |
Jan. 1, 2001 |
|
IV |
25 |
Jan. 2, 2001 |
Jan 26, 2001 |
The entire project must be
completed by Jan 26, 2001
40 days time allowed/permitted to
Applistech for "De-bugging" will not be counted for Project
Completion Date however the final 20% payment will be made, not at the
end of Phase IV but only after the "De-bugging" period.