3
July 2003
Kartvya/Reena,
BROADLAND
CENNECTION
·
You
told me that you were ready with a “Quote” from DSL & tat you & Abhi
have discussed it with Nirmit.
·
You
also said that, from the moment we release our order, DSL will take 2 Wks to
connect.
·
I
understand decision is to continue with existing 64 Kbps like in existing
office & connect new 128 kbps line at the new office where Tech. team will
move.
·
We
are likely to take possession of an 8th floor flat in the opposite
building on next Tuesday (8th). Then it may take 2 wks to break some
walls/re-plaster/repaint/fix power & LAN cables/fix wall-mounted tables for
work-stations/fix a/c etc.. That takes us to 23rd.
·
Please
co-ordinate with all concerned (including with Dharmishtaben-our Interior
Designer), to ensure that all above mentioned jobs-inclu.
getting / fixing 128 kbps
line – positively gets over by 23rd Actual shifting must take place
on 26th /27th list.
No comments:
Post a Comment