(Build2 Plan for Viky)
|
ID |
Task Name |
Duration |
Start |
Finish |
Predec |
7/13 |
7/20 |
7/27 |
August 8/3 |
|
5 |
Design |
20 days |
Mon 5/12/03 |
Wed 6/4/03 |
|||||
|
14 |
Setup |
2 days |
Tue 5/13/03 |
Wed 5/14/03 |
|||||
|
17 |
Build1 Development |
55.8 days |
Mon 5/12/03 |
Sat 7/19/03 |
|||||
|
83 |
Build1 Unit Testing &
Release |
24 days |
Fri 6/13/03 |
Mon 7/14/03 |
|||||
|
95 |
Implement VSS |
1 day |
Tue 7/15/03 |
Tue 7/15/03 |
|||||
|
96 |
Build2 Development |
41 days |
Thu 6/12/03 |
Sat 8/2/03 |
|||||
|
104 |
Business Logic Layer |
10 days |
Thu 7/17/03 |
Tue 7/29/03 |
|||||
|
108 |
BLGP Export to Excel, XML |
1.5 days |
Thu 7/17/03 |
Fri 7/18/03 |
125 |
||||
|
109 |
WSRM Download |
1 day |
Sat 7/19/03 |
Sat 7/19/03 |
108 |
||||
|
115 |
UI Layer |
11 days |
Tue 7/15/03 |
Mon 7/28/03 |
|||||
|
125 |
UIRMC Upload (using FTP) |
1.5 days |
Wed 7/16/03 |
Thu 7/17/03 |
95 |
||||
|
126 |
UIGP Person List - Part 2 List
Functions-Verify, MailMerge, Download/Export, Beautification) |
2 days |
Mon 7/21/03 |
Tue 7/22/03 |
109 |
||||
|
127 |
UIGP Email to Candidates
(Verify, Communicate) |
2 days |
Wed 7/23/03 |
Thu 7/24/03 |
126 |
Project: ResumMine Commercial
Version
Date: Tue 7/15/03
|
ID |
Task Name |
Duration |
Start |
Finish |
Predec |
7/13 |
7/20 |
7/27 |
August 8/3 |
|
128 |
UIGP New Registration |
1 day |
Fri 7/25/03 |
Fri 7/25/03 |
127 |
||||
|
129 |
Integration with Home Page,
other links, Resolve Navigational issues |
1 day |
Mon 7/28/03 |
Mon 7/28/03 |
128 |
||||
|
130 |
Installation |
41 days |
Thu 6/12/03 |
Sat 8/2/03 |
|||||
|
132 |
Installation Program -
Application |
2 days |
Fri 8/1/03 |
Sat 8/2/03 |
136 |
||||
|
133 |
Build2 Unit Testing &
Release |
3.5 days |
Wed 7/30/03 |
Sat 8/2/03 |
|||||
|
134 |
Build1 Bug-fixes |
1 day |
Wed 7/30/03 |
Wed 7/30/03 |
129 |
||||
|
135 |
Test own programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
134 |
||||
|
136 |
Test other's programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
135 |
||||
|
144 |
Build3 Development |
7.5 days |
Mon 8/4/03 |
Wed 8/13/03 |
|||||
|
145 |
Performance Tuning |
5 days |
Mon 8/4/03 |
Fri 8/8/03 |
138,12 |
||||
|
146 |
Build Installation Fixes |
1 day |
Wed 8/6/03 |
Thu 8/7/03 |
141 |
||||
|
147 |
Build2 Bug-fixes |
3 days |
Thu 8/7/03 |
Tue 8/12/03 |
146 |
||||
|
148 |
Unit Test Build3 & Release |
1 day |
Tue 8/12/03 |
Wed 8/13/03 |
147 |
Project: ResumMine Commercial
Version
Date: Tue 7/15/03
(Build2 Plan for Vikram)
|
ID |
Task Name |
Duration |
Start |
Finish |
Predec |
7/13 |
7/20 |
7/27 |
August 8/3 |
|
1 |
.Net Training |
17.5 days |
Mon 5/12/03 |
Mon 6/2/03 |
|||||
|
14 |
Setup |
2 days |
Tue 5/13/03 |
Wed 5/14/03 |
|||||
|
17 |
Build1 Development |
55.8 days |
Mon 5/12/03 |
Sat 7/19/03 |
|||||
|
83 |
Build1 Unit Testing &
Release |
24 days |
Fri 6/13/03 |
Mon 7/14/03 |
|||||
|
96 |
Build2 Development |
41 days |
Thu 6/12/03 |
Sat 8/2/03 |
|||||
|
98 |
Data Access Layer |
4 days |
Wed 7/16/03 |
Sat 7/19/03 |
|||||
|
99 |
DA Schedules |
1 day |
Wed 7/16/03 |
Wed 7/16/03 |
95 |
||||
|
104 |
Business Logic Layer |
10 days |
Thu 7/17/03 |
Tue 7/29/03 |
|||||
|
105 |
BLGP Scheduler - Windows
Service for batch extrac |
4 days |
Thu 7/17/03 |
Mon 7/21/03 |
99 |
||||
|
111 |
Improve Extraction Accuracy |
2 days |
Mon 7/28/03 |
Tue 7/29/03 |
119,12 |
||||
|
115 |
UI Layer |
11 days |
Tue 7/15/03 |
Mon 7/28/03 |
|||||
|
120 |
UIRMC StatusOfExtraction |
1 day |
Tue 7/22/03 |
Tue 7/22/03 |
105 |
Project: ResumMine Commercial
Version
Date: Tue 7/15/03
|
ID |
Task Name |
Duration |
Start |
Finish |
Predec |
7/13 |
7/20 |
7/27 |
August 8/3 |
|
121 |
UIGP Inbox Reader |
3 days |
Wed 7/23/03 |
Fri 7/25/03 |
120 |
||||
|
133 |
Build2 Unit Testing &
Release |
3.5 days |
Wed 7/30/03 |
Sat 8/2/03 |
|||||
|
134 |
Build1 Bug-fixes |
1 day |
Wed 7/30/03 |
Wed 7/30/03 |
129 |
||||
|
135 |
Test own programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
134 |
||||
|
136 |
Test other's programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
135 |
||||
|
137 |
Bug Fix Unit Test defects |
1 day |
Fri 8/1/03 |
Fri 8/1/03 |
136 |
||||
|
144 |
Build3 Development |
7.5 days |
Mon 8/4/03 |
Wed 8/13/03 |
|||||
|
147 |
Build2 Bug-fixes |
3 days |
Thu 8/7/03 |
Tue 8/12/03 |
146 |
||||
|
148 |
Unit Test Build3 & Release |
1 day |
Tue 8/12/03 |
Wed 8/13/03 |
147 |
Project: ResumMine Commercial
Version
Date: Tue 7/15/03