3P Consultants P Ltd
Build2 Plan for Sunitha
(Handwritten note)
July 15, '03 (Handwritten note)
|
ID |
Task Name |
Duration |
Start |
Finish |
Predex |
|
1 |
.Net Training |
17.65 days |
Mon 5/12/03 |
Mon 6/2/03 |
|
|
5 |
Design |
20 days |
Mon 5/12/03 |
Wed 6/4/03 |
|
|
14 |
Setup |
2 days |
Tue 6/3/03 |
Wed 6/4/03 |
|
|
17 |
Build1 Development |
55.8 days |
Mon 5/12/03 |
Sat 7/19/03 |
|
|
83 |
Build1 Unit Testing &
Release |
24 days |
Fri 6/13/03 |
Mon 7/14/03 |
|
|
95 |
Implement VSS |
1 day |
Tue 7/15/03 |
Tue 7/15/03 |
|
|
96 |
Build2 Development |
41 days |
Thu 6/12/03 |
Sat 8/2/03 |
|
|
98 |
Data Access Layer |
4 days |
Wed 7/16/03 |
Sat 7/19/03 |
|
|
100 |
DA Counters |
1 day |
Wed 7/16/03 |
Wed 7/16/03 |
97 |
|
101 |
DA Person Ratings |
0.5 days |
Sat 7/19/03 |
Sat 7/19/03 |
106 |
|
102 |
DA Company/Business |
0.5 days |
Sat 7/19/03 |
Sat 7/19/03 |
101 |
|
104 |
Business Logic Layer |
10 days |
Thu 7/17/03 |
Tue 7/29/03 |
|
|
106 |
BLGP Counter, Implement in all
classes/UI |
2 days |
Thu 7/17/03 |
Fri 7/18/03 |
100 |
|
111 |
Improve Extraction Accuracy |
2 days |
Mon 7/28/03 |
Tue 7/29/03 |
119, 12 |
|
112 |
BL Admin Classes |
2.5 days |
Mon 7/21/03 |
Wed 7/23/03 |
Project: Resumine Commercial
Version
Date: Tue 7/15/03
Page: 1/2
Name: Kartavya Chitala
3P Consultants P Ltd
|
ID |
Task Name |
Duration |
Start |
Finish |
Predex |
|
113 |
BLA Users, Connectivity |
0.5 days |
Mon 7/21/03 |
Mon 7/21/03 |
102 |
|
114 |
BLA Environment |
1 day |
Tue 7/22/03 |
Wed 7/23/03 |
117 |
|
115 |
UI Layer |
11 days |
Tue 7/15/03 |
Mon 7/28/03 |
|
|
116 |
UI Admin Classes |
3.5 days |
Mon 7/21/03 |
Thu 7/24/03 |
|
|
117 |
UIA Users |
1 day |
Mon 7/21/03 |
Tue 7/22/03 |
113 |
|
118 |
UIA Environment |
0.5 days |
Wed 7/23/03 |
Wed 7/23/03 |
114 |
|
119 |
UIA Usage Statistics |
0.5 days |
Thu 7/24/03 |
Thu 7/24/03 |
118 |
|
133 |
Build2 Unit Testing &
Release |
3.5 days |
Wed 7/30/03 |
Sat 8/2/03 |
|
|
134 |
Build1 Bug-fixes |
1 day |
Wed 7/30/03 |
Wed 7/30/03 |
129 |
|
135 |
Test own programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
134 |
|
136 |
Test other's programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
135 |
|
137 |
Bug Fix Unit Test defects |
1 day |
Fri 8/1/03 |
Fri 8/1/03 |
136 |
|
144 |
Build3 Development |
7.5 days |
Mon 8/4/03 |
Wed 8/13/03 |
|
|
147 |
Build2 Bug-fixes |
3 days |
Thu 8/7/03 |
Tue 8/12/03 |
146 |
|
148 |
Unit Test Build3 & Release |
1 day |
Tue 8/12/03 |
Wed 8/13/03 |
147 |
Project: Resumine Commercial
Version
Date: Tue 7/15/03
Page: 2/2
Name: Kartavya Chitala
3P Consultants P Ltd
Build2 Plan for Reji (Handwritten
note)
July 15, '03 (Handwritten note)
|
ID |
Task Name |
Duration |
Start |
Finish |
Predex |
|
1 |
.Net Training |
17.65 days |
Mon 5/12/03 |
Mon 6/2/03 |
|
|
5 |
Design |
20 days |
Mon 5/12/03 |
Wed 6/4/03 |
|
|
17 |
Build1 Development |
55.8 days |
Mon 5/12/03 |
Sat 7/19/03 |
|
|
83 |
Build1 Unit Testing &
Release |
24 days |
Fri 6/13/03 |
Mon 7/14/03 |
|
|
96 |
Build2 Development |
41 days |
Thu 6/12/03 |
Sat 8/2/03 |
|
|
98 |
Data Access Layer |
4 days |
Wed 7/16/03 |
Sat 7/19/03 |
|
|
103 |
DA Profile Modifiers |
0.5 days |
Sat 7/19/03 |
Sat 7/19/03 |
122 |
|
104 |
Business Logic Layer |
10 days |
Thu 7/17/03 |
Tue 7/29/03 |
|
|
107 |
BLGP Export to Word
(re-formatted) |
2 days |
Sat 7/19/03 |
Tue 7/22/03 |
103 |
|
110 |
BLRS Spider |
1.5 days |
Thu 7/24/03 |
Fri 7/25/03 |
123 |
|
115 |
UI Layer |
11 days |
Tue 7/15/03 |
Mon 7/28/03 |
|
|
122 |
UIGP PersonDetailsP4 (Add,
Verify, KW Modifier, FN related KW, Pr. Modifiers, UpdateBy, Ratings) |
4 days |
Tue 7/15/03 |
Fri 7/18/03 |
Project: Resumine Commercial
Version
Date: Tue 7/15/03
Page: 1/2
Name: Kartavya Chitala
3P Consultants P Ltd
|
ID |
Task Name |
Duration |
Start |
Finish |
Predex |
|
123 |
UIRS Search Part2 (Function,
Designation, Edu, %tile, Location, Special Conditions) |
2 days |
Tue 7/22/03 |
Thu 7/24/03 |
107 |
|
124 |
UIRS Spider |
1 day |
Mon 7/28/03 |
Mon 7/28/03 |
110 |
|
133 |
Build2 Unit Testing &
Release |
3.5 days |
Wed 7/30/03 |
Sat 8/2/03 |
|
|
134 |
Build1 Bug-fixes |
1 day |
Wed 7/30/03 |
Wed 7/30/03 |
129 |
|
135 |
Test own programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
134 |
|
136 |
Test other's programs |
0.5 days |
Thu 7/31/03 |
Thu 7/31/03 |
135 |
|
137 |
Bug Fix Unit Test defects |
1 day |
Fri 8/1/03 |
Fri 8/1/03 |
136 |
|
138 |
Create Build2, release to QA |
0.5 days |
Sat 8/2/03 |
Sat 8/2/03 |
137 |
|
144 |
Build3 Development |
7.5 days |
Mon 8/4/03 |
Wed 8/13/03 |
|
|
147 |
Build2 Bug-fixes |
3 days |
Thu 8/7/03 |
Tue 8/12/03 |
146 |
|
148 |
Unit Test Build3 & Release |
1 day |
Tue 8/12/03 |
Wed 8/13/03 |
147 |
Project: Resumine Commercial
Version
Date: Tue 7/15/03
Page: 2/2
Name: Kartavya Chitala




No comments: