Nimit
Mr. K. Sudhakar
Manager - Sales
Applitech Solution Limited
Ahmedabad.
Sept. 14, 2000
Dear Mr. Sudhakar,
Purchase Order
Please treat this as our Purchase
Order for development & installation at our premises, a customized software
for Internal Management System for Order Execution & MIS.
This order is being released in
response to your revised offer dt Sept. 12, 2000, but with following changes as
agreed upon over telephone yesterday and in our meeting this morning:
$\triangleright$ Price
The price will be Rs. 8.25 lakhs
(Rupees Eight Lakh and Twenty-five Thousand only).
$\triangleright$ Penalty
Clause
For each phase, you have
quoted certain no. of days
required to complete the phase. These are given in Annex: A.
From this Annex: A, completion
date will be calculated for each phase. This will be called "Phase
Completion Date" (PCD).
For any delay in actual
completion of a given phase, beyond PCD, a penalty will be levied at the rate
of 0.5% of the total order value for each week (or part thereof) of the
delay. However, the total penalty will be limited to 5% of the
order-value.
$\triangleright$ Start of the
Project
Allowing you 10 days to
mobilise your manpower resources and for intimating to us, the
names/qualifications/past experience of your team-members who will work on our
project, Phase I shall commence on Monday, Sept 25.
$\triangleright$ Phase-Wise
Completion Dates
These will be as per Annex: B
If there is a likelihood of delay
in completion of any phase, you will inform us in writing about the same in
advance. This will, however, not change/alter the PCD as far as the application
of Penalty Clause is concerned.1
By same token, any time saved in
completion of an earlier phase, could be utilised for execution of the
subsequent phase, without altering the PCD for the subsequent dat2e.
$\triangleright$ Other Terms
& Conditions
These will remain same as per
your offer dt. Sept. 12, 2000, except to the extent as modified above.
$\triangleright$ Enclosed find
our cheque no 412944 dt 14/9/2000 for Rs. 1.65 Lakhs
Kindly sign & return
duplicate copy of this letter by way of your acceptance.
With regards
Accepted:
_______________
Sign.
H. Doshi
3 P Consultant
Date: Sept. 14, 2000.
Annex: A
ORDER EXECUTION MODULE
(Internal Management System)
COMPARISON OF OFFERS BY
APPLITECH
|
Phase/Stage |
No. of Days Required to
Complete the Phase |
|
As per Aug. Offer |
|
|
I - System Requirement Study |
10 |
|
II - Design & System
Specs. Physical Design. |
30 |
|
III -
Coding/Testing/Documentation/User Acceptance Testing |
40 |
|
IV - Installation of
Software/Training |
20 |
|
Total |
100 |
|
V - Debugging till
fault-free Operation of Software. |
40 |