Hi Friends,

Even as I launch this today ( my 80th Birthday ), I realize that there is yet so much to say and do. There is just no time to look back, no time to wonder,"Will anyone read these pages?"

With regards,
Hemen Parekh
27 June 2013

Now as I approach my 90th birthday ( 27 June 2023 ) , I invite you to visit my Digital Avatar ( www.hemenparekh.ai ) – and continue chatting with me , even when I am no more here physically

Translate

Thursday, 4 April 2002

EXHIBIT - H

THREE P CONSULTANTS PVT. LTD.

B-1, Lok Bharati Complex,

Marol Maroshi Road, Andheri (E),

Mumbai - 400 059. INDIA

Tel. : (91-22) 850 5800

Fax : (91-22) 850 6663

E-mail : contact@3pjobs.com

Web : www.3pjobs.com

Mr. Shahid Saiyed

General Manager

Applitech Solutions Ltd.

Ahmedabad - 310009

April 4, 2002

Dear Mr. Saiyed:

Order Execution System Software

I refer to

  • My letter/legal notice, dt. Dec. 21, 2001
  • Mr. Balwant Sharma's visit (along with Neeraj) to our office on Feb. 6, 2002
  • Sanjeev's email to Neeraj/Yogesh dt. April 2, 2002, summarising the latest position as spelled-out in our various emails dated
    • Feb. 2, 2002
    • Feb. 5, 2002
    • Feb. 14, 2002
    • Feb. 20, 2002
    • Feb. 22, 2002
    • Feb. 26, 2002
    • March 11, 2002

For your ready reference, I enclose a copy of this summary. From this summary, you will notice that, even as of today, - and despite Mr. Sharma's personal promise made during his visit to our office on Feb. 6 - the Order Execution System Software continues to be defective / dysfunctional / full of bugs.

You will also notice that, all throughout - before and after Mr. Sharma's visit on Feb. 6 - we have been regularly bringing to your notice (thru our emails), various problems / difficulties being faced by us in using this software.

It is now,

14 months since the originally promised delivery / installation / commissioning date of Jan 26, 2001.

Nearly 2 months since Mr. Sharma's personal visit on Feb. 6, when he promised to take care of all the remaining problems "within 2/3 weeks".

We are extremely distressed as a result of your failure to deliver a smoothly / satisfactorily working software till date. As a direct result of your non-delivery, our business has suffered very badly and is continuing to suffer badly. Our business-losses are mounting day-by-day.

Through our letter of Dec. 21, 2001, we have already served on you, our legal notice, demanding that

  • You immediately refund to us the amounts paid to you so far for the development of this software (approx. Rs. 5 lakhs)
  • You further immediately compensate us with a sum of Rs. 100 lakhs (Rupees One Hundred Lakhs) for the business losses suffered by us till Dec. 21, 2001

You were also requested to make the above-mentioned payments to us within ONE WEEK of our said letter dt. Dec. 21, 2001.

You have failed to make the above-mentioned payments to us. You have also failed to rectify the problems of the software.

In light of your failures, we reserve the rights to proceed against you and/or the directors of your Organisation, in a Court of law (including a Consumer Court), to legally recover the above-mentioned amounts. We also reserve our right to serve on your company, a winding-up petition.

With regards,

H.C. Parekh

Director

 




No comments: