Build 2 Overall Plan

3P Consultants P Ltd | July 15, '03

ID

Task Name

Duration

Start

Finish

Predec

1

Net Training

17.65 days

Mon 5/12/03

Mon 5/12/03

2

Hire Net Developer

0 days

Mon 5/12/03

Mon 5/12/03

3

Hire QA Engineer

0 days

Mon 5/12/03

Mon 5/12/03

4

Project Management

50 days

Mon 5/12/03

Fri 7/11/03

5

Design

20 days

Mon 5/12/03

Wed 6/4/03

14

Setup

2 days

Tue 5/13/03

Wed 5/14/03

17

Build1 Development

55.8 days

Mon 5/12/03

Sat 7/19/03

83

Build1 Unit Testing & Release

24 days

Fri 6/13/03

Mon 7/14/03

88

Build1 QA

36 days

Mon 6/9/03

Wed 7/23/03

89

Create Unit Test Plans

4 days

Mon 6/9/03

Wed 6/18/03

90

Create Integration Test Plans

2 days

Mon 6/9/03

Mon 6/11/03

89

91

Install Test Director

2 days

Mon 6/2/03

Wed 6/11/03

37

92

Feed Test Plans in TD

3 days

Tue 6/24/03

Thu 6/26/03

91, 90

93

Acceptance Test Build1

1 day

Tue 7/15/03

Tue 7/15/03

87

94

Details Test on Build1

7 days

Wed 7/23/03

Mon 8/11/03

142

95

Implement VSS

1 day

Tue 7/15/03

Tue 7/15/03

96

Build2 Development

41 days

Mon 6/2/03

Sat 8/2/03

97

Database Design for Counter, Scheduler & Rating

1 day

Tue 7/15/03

Tue 7/15/03

98

Data Access Layer

4 days

Wed 7/16/03

Sat 7/19/03

99

DA Schedules

1 day

Tue 7/22/03

Thu 7/24/03

107

100

DA Counters

1 day

Mon 5/12/03

Mon 5/12/03

101

DA Person Ratings

0.5 days

Wed 7/16/03

Thu 7/17/03

95

102

DA Company/Business

0.5 days

Sat 7/19/03

Sat 7/19/03

101

103

DA Profile Modifiers

0.5 days

Sat 7/19/03

Sat 7/19/03

122

104

Business Logic Layer

10 days

Thu 7/17/03

Tue 7/29/03

 

3P Consultants P Ltd | Page 2/3

ID

Task Name

Duration

Start

Finish

Predec

105

BLGP Scheduler - Windows Service for batch extrac

4 days

Thu 7/17/03

Mon 7/21/03

99

106

BLGP Counter, Implement in all classes/UI

2 days

Thu 7/17/03

Fri 7/18/03

100

107

BLGP Export to Word (re-formatted)

2 days

Sat 7/19/03

Tue 7/22/03

103

108

BLGP Export to Excel, XML

1.5 days

Thu 7/17/03

Fri 7/18/03

125

109

WSRM Download

1 day

Sat 7/19/03

Sat 7/19/03

108

110

BLRS Spider

2 days

Tue 5/13/03

Wed 5/14/03

111

Improve Extraction Accuracy

2 days

Mon 7/28/03

Tue 7/29/03

119, 112

112

BL Admin Classes

2.5 days

Mon 7/21/03

Mon 7/28/03

113

BLA Users, Connectivity

0.5 days

Mon 7/21/03

Mon 7/21/03

102

114

BLA Enviornment

1 day

Tue 7/22/03

Tue 7/22/03

117

115

UI Layer

11 days

Tue 7/15/03

Mon 8/11/03

116

UI Admin Classes

3.5 days

Mon 7/21/03

Wed 7/30/03

117

UIA Users

1 day

Tue 7/22/03

Tue 7/22/03

113

118

UIA Environment

0.5 days

Wed 7/23/03

Wed 7/23/03

114

119

UIA Usage Statistics

0.5 days

Wed 7/23/03

Wed 7/23/03

118

120

UIRMC StatusOfExtraction

1 day

Tue 7/22/03

Tue 7/22/03

105

121

UIGP Inbox Reader

3 days

Wed 7/23/03

Fri 7/25/03

120

122

UIGP PersonDetailsP4 (Add, Verify, VW Highlight,

4 days

Tue 7/15/03

Fri 7/18/03

123

Fill related KW, Pr, Modifiers, UpdateBy, Ratings)

124

UIRS Search Part2 (Function, Designation, Edu,

2 days

Tue 7/22/03

Thu 7/24/03

107

125

%Ile, Location, Special Conditions)

126

UIRS Spider

1 day

Mon 7/21/03

Mon 7/21/03

100

127

UIRMC Upload (using FTP)

1.5 days

Wed 7/16/03

Thu 7/17/03

95

128

UIGP Person List - Part 2 (List Functions-Verify,

2 days

Mon 7/21/03

Tue 7/22/03

109

129

MailMerge, Download/Export, Beautification)

130

UIGP Email to Candidates (Verify, Communicate)

2 days

Wed 7/23/03

Thu 7/24/03

126

131

UIGP New Registration

1 day

Fri 7/25/03

Fri 7/25/03

127

3P Consultants P Ltd | August | Page 3/3

ID

Task Name

Duration

Start

Finish

Predec

129

Integration with Home Page, other links, Resolve

1 day

Mon 7/28/03

Mon 7/28/03

128

130

Navigational issues

131

Installation

41 days

Thu 6/12/03

Sat 8/2/03

132

Installation Program - Database

4 days

Thu 6/12/03

Tue 6/17/03

91

133

Installation Program - Application

2 days

Fri 8/1/03

Sat 8/2/03

136

134

Build2 Unit Testing & Release

3.5 days

Wed 7/30/03

Sat 8/2/03

135

Build1 Bug-fixes

1 day

Wed 7/30/03

Wed 7/30/03

129

136

Test own programs

0.5 days

Thu 7/31/03

Thu 7/31/03

134

137

Test other's programs

0.5 days

Thu 7/31/03

Thu 7/31/03

135

138

Bug Fix Unit Test defects

1 day

Fri 8/1/03

Fri 8/1/03

136

139

Create Build2, release to QA

0.5 days

Sat 8/2/03

Sat 8/2/03

137

140

Build2 QA

6 days

Sat 8/2/03

Mon 8/11/03

141

Acceptance Test Build2

1 day

Sat 8/2/03

Wed 8/6/03

37

142

Installation Test Build2

2 days

Mon 8/4/03

Wed 8/6/03

140

143

Detailed Test on Build2

2 days

Wed 8/6/03

Fri 8/8/03

141

144

Performance Test Build2

1 day

Fri 8/8/03

Mon 8/11/03

142

145

Build3 Development

7.5 days

Mon 8/4/03

Wed 8/13/03

146

Performance Tuning

5 days

Mon 8/4/03

Fri 8/8/03

138, 12

147

Build2 Installation Fixes

1 day

Wed 8/6/03

Thu 8/7/03

141

148

Build2 Bug-fixes

3 days

Thu 8/7/03

Tue 8/12/03

146

149

Unit Test Build3 & Release

1 day

Tue 8/12/03

Wed 8/13/03

147

150

User Manuals / Online Help

0 days

Mon 5/12/03

Mon 5/12/03

151

Beta

36 days

Wed 8/13/03

Fri 9/26/03

152

Scope for change

24 days

Thu 8/28/03

Fri 9/26/03

151

  