Friday, 14 February 2003

PROJECT PLAN

 

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

1

Phase1

24 days

Tue 2/11/03

Mon 3/10/03

2

Design & Estimate

6.5 days

Wed 2/12/03

Wed 2/19/03

4

Functional Specifications

2 days

Thu 2/13/03

Fri 2/14/03

HCP, Kartaraya

9

Build1

17 days

Tue 2/11/03

Sat 3/1/03

21

Refine Functions & Keywords

17 days

Tue 2/11/03

Sat 3/1/03

Inder, HCP

54

Demo

13.5 days

Sat 2/22/03

Mon 3/10/03

58

Prepare FAQs

1 day

Tue 2/25/03

Wed 2/26/03

42

Abhi, Kartaraya, HCP

59

Prepare answers to FAQs

2 days

Mon 2/24/03

Wed 2/26/03

58

Kartaraya, Abhi, HCP

(Kartaraya)

ID

Task Name

Duration

 

Start

Finish

Preds

Resource Names

1

Phase1

24 days

 

Tue 2/11/03

Mon 3/10/03

2

Design & Estimate

6.5 days

 

Wed 2/12/03

Wed 2/19/03

3

Prepare Draft Project Plan

1 day

 

Wed 2/12/03

Wed 2/12/03

Kartaraya

4

Functional Specifications

2 days

 

Thu 2/13/03

Fri 2/14/03

HCP, Kartaraya

5

Technical Design

2 days

 

Mon 2/17/03

Tue 2/18/03

4

Kartaraya, Abhi

6

Database Design

1 day

 

Tue 2/18/03

Tue 2/18/03

5

Kartaraya, Abhi

7

Finalize Project Plan

0.5 days

 

Wed 2/19/03

Wed 2/19/03

6

Kartaraya, Abhi

8

Incorporate Version Control

1 day

 

Thu 2/20/03

Fri 2/21/03

7

Kartaraya

9

Build1

17 days

 

Tue 2/11/03

Sat 3/1/03

22

Create new IT Functions

1 day

 

Thu 2/13/03

Thu 2/13/03

Kartaraya

30

Build2

23 days

 

Tue 2/11/03

Sat 3/8/03

49

Build2 QA - Performance

2 days

 

Mon 3/3/03

Tue 3/4/03

47

Kartaraya

53

Performance Improvement

3 days

 

Thu 3/6/03

Sat 3/8/03

52

Abhi, Sunitha, Kartaraya

54

Demo

13.5 days

 

Sat 2/22/03

Mon 3/10/03

56

Install Modul1 for Demo

1 day

 

Tue 2/25/03

Wed 2/26/03

42

Abhi

58

Prepare FAQs

1 day

 

Tue 2/25/03

Wed 2/26/03

42

Abhi, Kartaraya, HCP

59

Prepare answers to FAQs

2 days

 

Mon 2/24/03

Wed 2/26/03

58

Kartaraya, Abhi, HCP

60

Rehearsal Demo

1 day

 

Mon 3/10/03

Mon 3/10/03

53

Kartaraya, Abhi

(Abhi)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

1

Phase1

24 days

Tue 2/11/03

Mon 3/10/03

2

Design & Estimate

6.5 days

Wed 2/12/03

Wed 2/19/03

5

Technical Design

2 days

Mon 2/17/03

Tue 2/18/03

4

Kartaraya, Abhi

6

Database Design

1 day

Tue 2/18/03

Tue 2/18/03

5

Kartaraya, Abhi

7

Finalize Project Plan

0.5 days

Wed 2/19/03

Wed 2/19/03

6

Kartaraya, Abhi

9

Build1

17 days

Tue 2/11/03

Sat 3/1/03

21

Refine Functions & Keywords

17 days

Tue 2/11/03

Sat 3/1/03

Kartaraya, Abhi

22

Create new IT Functions

1 day

Thu 2/13/03

Thu 2/13/03

Kartaraya, Abhi

30

Build2

23 days

Tue 2/11/03

Sat 3/8/03

33

Module1 Changes

5 days

Wed 2/26/03

Mon 3/3/03

36

Multiple Functions per Candidate

2 days

Sat 2/22/03

Mon 2/24/03

35

Reji, Abhi

53

Performance Improvement

3 days

Thu 3/6/03

Sat 3/8/03

52

Abhi, Sunitha, Kartaraya

54

Demo

13.5 days

Sat 2/22/03

Mon 3/10/03

56

Install Modul1 for Demo

1 day

Tue 2/25/03

Wed 2/26/03

42

Abhi

58

Prepare FAQs

1 day

Tue 2/25/03

Wed 2/26/03

42

Abhi, Kartaraya, HCP

59

Prepare answers to FAQs

2 days

Mon 2/24/03

Wed 2/26/03

58

Kartaraya, Abhi, HCP

60

Rehearsal Demo

1 day

Mon 3/10/03

Mon 3/10/03

53

Kartaraya, Abhi

 (Reji)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

1

Phase1

24 days

Tue 2/11/03

Mon 3/10/03

9

Build1

17 days

Tue 2/11/03

Sat 3/1/03

27

Build1 QA - Functional Part1

5 days

Tue 2/11/03

Sat 2/15/03

Reji

28

Build1 QA - Performance

2 days

Tue 2/11/03

Wed 2/12/03

Reji

30

Build2

23 days

Tue 2/11/03

Sat 3/8/03

33

Module1 Changes

5 days

Wed 2/26/03

Mon 2/28/03

Reji

34

Modify Display Format & Show Pri

2 days

Wed 2/26/03

Thu 2/27/03

Reji

35

Merge Keyword Categories

1 day

Fri 2/28/03

Fri 2/28/03

34

Reji

36

Multiple Functions per Candidate

2 days

Sat 2/22/03

Mon 2/24/03

35

Reji, Abhi

37

Various File Formats

14 days

Tue 2/11/03

Wed 2/26/03

44

Integrate Function Profiler

2 days

Tue 2/25/03

Wed 2/26/03

40

Reji

45

Display Missing Keywords

0.5 days

Thu 2/27/03

Thu 2/27/03

41

Reji

47

Display Profile Enhancers

0.5 days

Sat 3/1/03

Sat 3/1/03

45

Reji

52

Fix Build2 Defects - Reji

0.5 days

Sat 3/1/03

Sat 3/1/03

48

Reji

54

Demo

13.5 days

Sat 2/22/03

Mon 3/10/03

55

Install Resume Extractor for Demo

0.5 days

Mon 3/10/03

Mon 3/10/03

53

Reji

 (Vikram)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

9

Build1

17 days

Tue 2/11/03

Sat 3/1/03

10

Extraction Development

9 days

Tue 2/11/03

Thu 2/20/03

11

Extract Current Company

2 days

Tue 2/11/03

Wed 2/12/03

Vikram

12

Extract Current Designation

3 days

Fri 2/14/03

Mon 2/17/03

11

Vikram

13

Extract Industry

1 day

Tue 2/18/03

Tue 2/18/03

12

Vikram

16

Extract Address (Cont.)

0.5 days

Wed 2/19/03

Wed 2/19/03

13

Vikram

17

Extract Contact Details (Cont.)

0.5 days

Thu 2/20/03

Thu 2/20/03

16

Vikram

18

Extract Biode

1 day

Wed 2/19/03

Wed 2/19/03

17

Vikram

20

Extract Years of Experience (Cont)

0.5 days

Thu 2/20/03

Thu 2/20/03

19

Vikram

30

Build2

23 days

Tue 2/11/03

Sat 3/8/03

32

Fix Build1 Defects - Vikram

1 day

Mon 2/24/03

Mon 2/24/03

20

Vikram

43

Field Highlight Feature

1 day

Tue 2/25/03

Tue 2/25/03

32

Vikram

48

Build2 QA - Functional

4 days

Wed 2/26/03

Sat 3/1/03

43

Sunitha (50%), Vikram

51

Fix Build2 Defects - Vikram

3 days

Mon 3/3/03

Wed 3/5/03

48

Vikram

(Sunitha)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

1

Phase1

24 days

Tue 2/11/03

Mon 3/10/03

10

Extraction Development

9 days

Tue 2/11/03

Thu 2/20/03

14

Extract Educ - Degree, Disc & Levi

2 days

Tue 2/11/03

Wed 2/12/03

Sunitha

15

Extract Name (Cont.)

0.5 days

Mon 2/17/03

Mon 2/17/03

14

Sunitha

19

Extract Blocks (Cont.)

1 day

Mon 2/17/03

Tue 2/18/03

15

Sunitha

30

Build2

23 days

Tue 2/11/03

Sat 3/8/03

31

Fix Build Defects - Sunitha

1 day

Tue 2/18/03

Tue 2/18/03

Sunitha

37

Extract Functions

1 day

Thu 2/20/03

Thu 2/20/03

31

Sunitha

38

Various File Formats

14 days

Tue 2/11/03

Wed 2/26/03

40

DOC

1 day

Tue 2/11/03

Tue 2/11/03

Sunitha

42

Save to Database

2 days

Fri 2/21/03

Sat 2/22/03

37

Sunitha

46

Integrate Matchmaker

1 day

Tue 2/25/03

Tue 2/25/03

42

Sunitha

48

Build2 QA - Functional

4 days

Wed 2/26/03

Sat 3/1/03

43

Sunitha (50%), Vikram

50

Fix Build2 Defects - Sunitha

3 days

Mon 3/3/03

Wed 3/5/03

48

Sunitha

53

Performance Improvement

3 days

Thu 3/6/03

Sat 3/8/03

52

Abhi, Sunitha, Kartaraya

(Deepa)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

1

Phase1

24 days

Tue 2/11/03

Mon 3/10/03

54

Demo

13.5 days

Sat 2/22/03

Mon 3/10/03

57

Extract 5000 resumes

5 days

Thu 2/27/03

Wed 3/5/03

44

Deepa

(Project Plan - Page 1)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

1

Phase1

24 days

Tue 2/11/03

Mon 3/10/03

2

Design & Estimate

6.5 days

Wed 2/12/03

Wed 2/19/03

3

Prepare Draft Project Plan

1 day

Wed 2/12/03

Wed 2/12/03

Kartaraya

4

Functional Specifications

2 days

Thu 2/13/03

Fri 2/14/03

HCP, Kartaraya

5

Technical Design

2 days

Mon 2/17/03

Tue 2/18/03

4

Kartaraya, Abhi

6

Database Design

1 day

Tue 2/18/03

Tue 2/18/03

5

Kartaraya, Abhi

7

Finalize Project Plan

0.5 days

Wed 2/19/03

Wed 2/19/03

6

Kartaraya, Abhi

8

Incorporate Version Control

1 day

Thu 2/20/03

Fri 2/21/03

7

Kartaraya

9

Build1

17 days

Tue 2/11/03

Sat 3/1/03

10

Extraction Development

17 days

Tue 2/11/03

Sat 3/1/03

11

Extract Current Company

2 days

Tue 2/11/03

Wed 2/12/03

Vikram

12

Extract Current Designation

3 days

Fri 2/14/03

Mon 2/17/03

11

Vikram

13

Extract Industry

1 day

Tue 2/18/03

Tue 2/18/03

12

Vikram

14

Extract Educ - Degree, Disc & Levi

2 days

Tue 2/11/03

Wed 2/12/03

Sunitha

15

Extract Name (Cont.)

0.5 days

Mon 2/17/03

Mon 2/17/03

14

Sunitha

16

Extract Address (Cont.)

0.5 days

Wed 2/19/03

Wed 2/19/03

13

Vikram

17

Extract Contact Details (Cont.)

0.5 days

Thu 2/20/03

Thu 2/20/03

16

Vikram

18

Extract Biode

1 day

Wed 2/19/03

Wed 2/19/03

17

Vikram

19

Extract Blocks (Cont.)

1 day

Mon 2/17/03

Tue 2/18/03

15

Sunitha

20

Extract Years of Experience (Cont)

0.5 days

Thu 2/20/03

Thu 2/20/03

18

Vikram

21

Refine Functions & Keywords

17 days

Tue 2/11/03

Sat 3/1/03

22

Create new IT Functions

1 day

Thu 2/13/03

Thu 2/13/03

Kartaraya, Abhi

23

Refine Modifer Function

2 days

Fri 2/14/03

Sat 2/15/03

22

Kartaraya, Abhi

24

Mobile Functions Per Keywords

2 days

Tue 2/11/03

Wed 2/12/03

Inder

25

Regress / Integrate Keyworks

2 days

Thu 2/13/03

Fri 2/14/03

24

Inder

26

Add new Keywords

5 days

Sat 2/15/03

Fri 2/21/03

25

Inder, HCP

27

Build1 QA - Functional Part1

5 days

Tue 2/11/03

Sat 2/15/03

Reji

28

Build1 QA - Performance

2 days

Tue 2/11/03

Wed 2/12/03

Reji

29

Build1 QA - Functional Part2

2 days

Fri 2/21/03

Sat 2/22/03

26

Reji

30

Build2

23 days

Tue 2/11/03

Sat 3/8/03

31

Fix Build Defects - Sunitha

1 day

Tue 2/18/03

Tue 2/18/03

Sunitha

32

Fix Build1 Defects - Vikram

1 day

Mon 2/24/03

Mon 2/24/03

20

Vikram

33

Module1 Changes

5 days

Wed 2/26/03

Mon 3/3/03

34

Modify Display Format & Show Pri

2 days

Wed 2/26/03

Thu 2/27/03

Reji

35

Merge Keyword Categories

1 day

Fri 2/28/03

Fri 2/28/03

34

Reji

36

Multiple Functions per Candidate

2 days

Sat 2/22/03

Mon 2/24/03

35

Reji, Abhi

37

Extract Functions

1 day

Thu 2/20/03

Thu 2/20/03

31

Sunitha

38

Various File Formats

14 days

Tue 2/11/03

Wed 2/26/03

39

RTF

0 days

Tue 2/11/03

Tue 2/11/03

Reji

40

DOC

1 day

Fri 2/21/03

Fri 2/21/03

37

Sunitha

41

Monster

2 days

Tue 2/25/03

Wed 2/26/03

36

Reji

(Project Plan - Page 2)

ID

Task Name

Duration

Start

Finish

Preds

Resource Names

42

Save to Database

2 days

Fri 2/21/03

Sat 2/22/03

36

Sunitha

43

Field Highlight Feature

1 day

Tue 2/25/03

Tue 2/25/03

32

Vikram

44

Integrate Matchmaker

1 day

Tue 2/25/03

Tue 2/25/03

42

Sunitha

45

Integrate Function Profiler

2 days

Tue 2/25/03

Wed 2/26/03

41

Reji

46

Display Missing Keywords

0.5 days

Thu 2/27/03

Thu 2/27/03

41

Reji

47

Display Profile Enhancers

0.5 days

Sat 3/1/03

Sat 3/1/03

45

Reji

48

Build2 QA - Functional

4 days

Wed 2/26/03

Sat 3/1/03

43

Sunitha (50%), Vikram

49

Build2 QA - Performance

2 days

Mon 3/3/03

Tue 3/4/03

47

Kartaraya

50

Fix Build2 Defects - Sunitha

3 days

Mon 3/3/03

Wed 3/5/03

48

Sunitha

51

Fix Build2 Defects - Vikram

3 days

Mon 3/3/03

Wed 3/5/03

48

Vikram

52

Fix Build2 Defects - Reji

0.5 days

Sat 3/1/03

Sat 3/1/03

48

Reji

53

Performance Improvement

3 days

Thu 3/6/03

Sat 3/8/03

52

Abhi, Sunitha, Kartaraya

54

Demo

13.5 days

Sat 2/22/03

Mon 3/10/03

55

Install Resume Extractor for Demo

0.5 days

Mon 3/10/03

Mon 3/10/03

53

Reji

56

Install Modul1 for Demo

1 day

Tue 2/25/03

Wed 2/26/03

42

Abhi

57

Extract 5000 resumes

5 days

Thu 2/27/03

Wed 3/5/03

44

Deepa

58

Prepare FAQs

1 day

Tue 2/25/03

Wed 2/26/03

22

Kartaraya, Abhi, HCP

59

Prepare answers to FAQs

2 days

Mon 2/24/03

Wed 2/26/03

58

Kartaraya, Abhi, HCP

60

Rehearsal Demo

1 day

Mon 3/10/03

Mon 3/10/03

53

Kartaraya, Abhi

61

Phase 2

1 day

Sat 3/15/03

Sat 3/15/03

62

Net Migration

1 day?

Tue 3/11/03

Tue 3/11/03

63

Output Formats

1 day?

Tue 3/11/03

Tue 3/11/03

64

Extract Work History Specifics

1 day?

Tue 3/11/03

Tue 3/11/03

65

Mobile Functions Path

1 day?

Tue 3/11/03

Tue 3/11/03

66

Extract Educ - Univ. & Yr. Of Pass

1 day?

Wed 2/12/03

Wed 2/12/03

67

Extract Extraction-failed Resumes

1 day

Tue 2/11/03

Tue 2/11/03

68

Duplicate Resolution

3 days

Tue 2/11/03

Thu 2/13/03

69

Bulk Processing Feature

5 days

Tue 2/11/03

Sat 2/15/03

70

Email Reader

3 days

Tue 2/11/03

Thu 2/13/03

71

Integrate Thesaurus

2 days

Tue 2/11/03

Wed 2/12/03

3P Organizational Chart - IT

Title

Name

CTO

Kartaraya Chitiala

Dy. Project Manager

Abhinandan K

Network Administrator

Reena Gund

Sr. Software Engineer

Sunitha Arvind

Sr. Software Engineer

Vikram Athalya

Sr. Software Engineer

TBD1

QA Lead

TBD2

Business Analyst

Inder Sethi

Software Engineer

Deepa T

Software Engineer

Reji Omen

Note to Staff:

To: All Staff Members (Individual Copies)

Management is pleased to announce following appointments, with effect from Feb 1, 2003:

  • Kartaraya - - - - - - Chief Technology Officer (CTO)
  • Abhinandan - - - - - - Dy. Project Manager

With a view to launching our webservice project as fast as possible, the IT team has been re-organised as shown above.

 












No comments: