EXHIBIT - E

Annex: B

PHASE COMPLETION DATES (PCD)

Phase

No. of Days

Starting Date

Completion Date

I

20

Sept. 25

Oct. 14

II

35

Oct. 15

Nov. 17

III

45

Nov. 18

Jan. 1, 2001

IV

25

Jan. 2, 2001

Jan 26, 2001

The entire project must be completed by Jan 26, 2001

40 days time allowed/permitted to Applistech for "De-bugging" will not be counted for Project Completion Date however the final 20% payment will be made, not at the end of Phase IV but only after the "De-bugging" period.

 